October 15, 2026
At 3 p.m. on Wednesday, September 30, the City of Lake Forest cut the ribbon on the new Lake & Woodbine Bridge. Guests parked on Ring Road in Forest Park, and that afternoon Lake Road reopened to traffic just north of Woodbine Lane for the first time since January. The new bridge has precast balustrades and a concrete arch profile, both drawn from the 1912 bridge it replaced.
Farther along Lake Road, the second Lake Road project is stopped. The Lake & Spruce Bridge, which the city's paperwork calls the McLennon-Reed Bridge, was supposed to be the easier job. It needed a new deck on a 1978 steel bridge, not a full rebuild. It has been on hold since the summer because of water in the ravine slope beneath it.
On paper, Woodbine was the harder project. It is the one that finished.
| Lake & Woodbine | Lake & Spruce / McLennon-Reed | |
|---|---|---|
| Location on Lake Road | Between Woodbine Lane and East Barberry Lane | Between Woodland Road and Spruce Avenue |
| Original structure | 1912 closed-spandrel concrete arch | 1978 steel bridge, three continuous spans totaling 173 feet |
| Scope | Full replacement | New deck, slope stabilization, channel restoration |
| Budget | $4.7 million, with $3.7 million from grants | $2.2 million budget; $2,175,000 contract awarded Nov. 17, 2025 |
| Contractor | Dunnet Bay Construction | Dunnet Bay Construction |
| Status as of Oct. 12, 2026 | Open to traffic since Sept. 30, with punch-list work remaining | Halted pending further geotechnical study |
Woodbine's scope was more than twice the budget of Spruce's. It had federal money attached and sat inside the East Lake Forest Historic District. That project came in on its nine-month construction window. The smaller deck replacement is the one with no reopening date.
The Woodbine bridge was slow in the stages that happen at a desk. Because it carried federal funding, the city had to follow IDOT's three-phase process. Planning, which covered bridge type studies, environmental reviews, and work with the Historic Preservation Commission, ran from 2012 to 2024. Design ran from 2023 to 2025, with reviews by IDOT and the State Historic Preservation Officer. The Historic Preservation Commission issued a Certificate of Appropriateness, finding that the design fit the historic district.
Then it was delayed by money. Construction was first expected in 2025, but budget constraints pushed it back. The city applied for a second grant to cover the added cost and received it in April 2025. Lake Road closed at the bridge the week of January 12, 2026. Local access stayed open on either side.
Once work began, the decade of preparation paid off. The original 1912 bridge had shallow closed-spandrel arches, piers, decorative relief panels, and balustrade railings, and the replacement echoes its closed-spandrel concrete-arch appearance. According to Civiltech's account of the project, the new structure was cast in place over extensive temporary formwork. It carries ornamental precast concrete balustrades modeled on the originals. In the same article, Civiltech resident engineer Hugh Gilgunn said the traditional methods were challenging. He also said it was gratifying to work on a design that honors the old bridge.
In the last full week before opening, crews spread topsoil, replaced brick paver driveways, finished the residential walls attached to the bridge, and seeded the ravine under erosion-control blanket. In short, the Woodbine schedule depended on approvals and funding, and once those were settled, construction was predictable.
The Spruce project had none of that history. The bridge dates to 1978. Its deck had been patched over the years with epoxy, concrete, and asphalt, and a concrete drainage channel ran beneath the center span. The plan called for a new concrete deck with a sidewalk along the east edge, new railings, and about 33 feet of slope stabilization directly beneath the bridge. The city's page expected an April start and about six months of work.
The October 5, 2026 City Council agenda lays out what happened after that, in order:
Sixty-four ounces is half a gallon. At that rate, the drains move about 720 gallons a day out of one embankment, and the agenda says the flow showed no sign of slowing. The city's page notes that some water was expected after winter snowmelt and spring rain. The flow kept going well past that season.
The ECS report gave the city some reassurance and some uncertainty. Four 100-foot soil borings found groundwater about 24 feet below grade, in a layer of sand. The borings could not show whether that water is a pocket at the sampling spots or runs consistently down the slope to the bottom of the ravine. ECS concluded that both ravine slopes are stable for now but need stabilization to meet the required long-term safety margin.
The agenda explains why the city chose not to start building fixes based on that report:
"Proceeding based on the current conservative groundwater assumptions would require more extensive stabilization measures than may be necessary, potentially resulting in increased construction costs."
Staff recommended more subsurface investigation to pin down the groundwater conditions first. The firm proposed for that work is Wiss, Janney, Elstner Associates, already the city's bridge program manager and structural engineer on this project. Its proposal is for up to $70,300. That would raise WJE's budget line from $80,000 to $144,731. The unbudgeted $64,731 would come from savings elsewhere in the FY2027 Capital Improvement Fund. The amendment is for engineering only. It is separate from the $2,175,000 construction contract.
One sentence in the agenda is easy to over-read. It says the additional work "will not alter the original target completion dates for this service." "This service" refers to WJE's engineering contract, not the bridge. The agenda gives no new reopening date for Lake Road at Spruce. The materials reviewed for this post include the request but not the Council's vote on it.
For anyone using Lake Road through the rest of October, the two ends now work differently.
The Lake Road Bridges project page is where Spruce updates will appear first. The city also sends email and text alerts to people who register at cityoflakeforest.com/enotify. The next real milestone for the McLennon-Reed Bridge is a refined groundwater picture from WJE's supplemental investigation. The stabilization design, and any reopening date, will follow from that.
The Woodbine bridge was rebuilt to keep the look of the East Lake Forest Historic District, and we pay the same attention to the homes along this stretch of Lake Road. If you live near either ravine and want to talk about how your home's setting and historic character come across to the next buyer, Kim & Carleigh would be glad to walk the property with you. Schedule a design-forward consultation.
Stay up to date on the latest real estate trends.
Kim and Carleigh craft tailored marketing strategies that maximize impact and elevate every listing. Their results-driven approach delivers exceptional outcomes for buyers and sellers alike.